Evanston’s dog beach has a closing date and, for the first time in a while, a rough idea of how it might come back. The off-leash beach will shut indefinitely on Dec. 1, and the city plans to go back out to bid this winter for a cheaper fix built around a pier-style ramp.
The beach has been out of compliance with the Americans with Disabilities Act since the City Council reopened it in October 2022. The paved path from the street ends at a gate and turns straight into sand, which leaves people who use wheelchairs with no way down to the water. The city has disclosed four formal complaints about it. None has become a lawsuit, but one resident who uses a power wheelchair wrote in an Aug. 14 grievance that the project had taken “far too long” and raised the possibility of going to the Illinois Department of Human Rights or federal court.
Why the last plan died
On Sept. 28, the council’s Administration and Public Works Committee unanimously rejected an $863,850 design-build contract with John Keno & Company. The city had budgeted about $650,000 when it sought proposals, and Keno was the only bidder. Covering the gap would have meant pairing $750,000 in 2025-26 bond money with another $113,850 against 2027 bonds. Alders called the design too expensive and too complicated for what it needed to do.
It was at least the fourth reset in two years. The council let an earlier Keno contract expire in July 2024, hired GEI Consultants for a second opinion in January 2025, and switched to a design-build bid in December 2025.
The replacement idea comes from Ald. Clare Kelly, whose 1st Ward includes the beach. In a memo, Public Works Director Edgar Cano, project manager Jason Krohn and City Engineer Lara Biggs said staff would come back with “a possibly less expensive ramp that is more direct and environmentally appropriate, minimizes shoreline hardening through the use of a pier-style structure and aims for installation by the 2027 summer season.” The city expects to issue the new request for proposals in December.
“We’ve been talking about it for far too long,” Kelly said at the meeting. “I think we’re now at a place where we can get this done quickly and in a far better way, both for the users, for the disabled community, for the environment, for dogs and for everyone else.” She said she was confident the beach could reopen with a compliant ramp by May 15.
Cano was more careful. He couldn’t say how much the redesign would save, only that it would likely cost less, and he flagged Army Corps of Engineers permitting for work on Lake Michigan as one of the open questions on the schedule.
Why the beach closes now
The city’s ADA Advisory Committee pushed for the closure a few days before the vote. At the request of chair Murphy Monroe, the committee recommended shutting the beach until it is “readily accessible to and usable by individuals with disabilities,” and said a temporary fix, like the mobility mats used at the swimming beaches, shouldn’t be enough to keep it open.
“Until there’s a fully bid and fully engineered plan, it’s not something you can vote on,” Monroe said, “and you can’t run an inaccessible beach.”
City attorney Alex Ruggie told alders that having a compliance plan underway might protect the city for now, but that “the best legal argument is to have that executed contract” before reopening. Parks and Recreation Director Audrey Thompson noted the beach already closes for much of the winter because of ice, and said a hard closure date would put “pressure on us to do what we’re supposed to do.” Ald. Jonathan Nieuwsma left room to revisit the closure once a plan is formally in place, even if the ramp isn’t built yet.
Owners push back
Dog owners haven’t taken it quietly. More than 100 people turned out Oct. 26 for a “bark-in” outside the Morton Civic Center at 909 Davis St., organized by the group Save Evanston Dog Beach, whose organizers include Phil Birnbaum and Katie Neenan. Online, the frustration runs in two directions: some residents are angry the city took four years to fix an entrance, while others question why it is spending this much on a dog beach at all.
What comes next
The next step is the bid document. If it goes out in December and contractors can price a pier-style ramp near the original budget, Kelly’s spring target is possible. If the bids come in high again, the council will face the same choice it had in September, this time with the beach already closed. Either way, Dec. 1 is the last day dogs can run on the sand until the ramp is built.
Add The Evanston Edge as a preferred source on Google (opens in a new tab)
Margaret Whitfield is the editor of The Evanston Edge and covers local government, development and neighborhoods.